Construction sequence of tunnel steel fiber reinforced concrete

Aug.17.2023       250

Construction sequence of tunnel steel fiber reinforced concrete


1、 Construction sequence of cave entrance


Excavation of soil and rock at the entrance of the tunnel → Setting up a circular intercepting ditch → Trimming the section and slope → Timely temporary reinforcement of the slope → Entering the tunnel


2、 Construction sequence of tunnel excavation


Class II and III surrounding rocks:


Measurement and layout → advanced support → excavation of advanced guide tunnel in the middle partition wall until it is fully connected → lining of the middle partition wall → advanced support → excavation of advanced guide tunnel in the left (right) side wall until it is fully connected → lining of the side wall → advanced support → excavation of the left (right) upper circular section (Class II) or the left (right) upper half section (Class III) → lining of the left (right) arch ring → excavation of the left (right) lower half section


Class IV surrounding rock:


Measurement and layout → Excavation of advanced guide tunnel for middle partition wall until it is fully connected → Lining of middle partition wall → Excavation of advanced guide tunnel for left (right) side wall until it is fully connected → Lining of side wall → Excavation of left (right) upper section → Lining of left (right) arch ring → Excavation of left (right) lower section


Note: After the construction of the partition wall is completed, excavation shall be carried out as a single hole.


3、 Construction sequence of tunnel lining


Measurement and layout → Middle partition wall lining → Left (right) side wall lining → Left (right) arch ring lining → Left (right) inverted arch lining (Class II-III rock) → Maintenance


Note: After the construction of the partition wall is completed, excavation shall be carried out as a single hole.


4、 Construction sequence of cement concrete pavement inside the tunnel


Acceptance of grassroots (or leveling layer) → measurement and layout → erection of formwork and placement of tie rods, etc. → concrete mixing → transportation of concrete to the construction site → paving of concrete → insertion and flat plate vibration → vacuum water absorption → mechanical leveling → manual smoothing and roughening → curing → cutting and grouting joints → curing






Construction sequence of steel fiber reinforced concrete for bridges


1、 Construction sequence of bored pile


Construction preparation → Measurement and layout → Setting up protective structures → Positioning drilling frame → Drilling and first hole cleaning → Placing steel cages, conduits, and second hole cleaning → Pouring underwater concrete → Measuring concrete surface elevation → End of conduit removal


2、 Expand the sequence of basic construction


Construction preparation → measurement and layout → cofferdam pumping → excavation of foundation pit → detection of foundation pit size → formwork erection → concrete mixing and pouring → maintenance


3、 Construction sequence of pier cap and pier body


Construction preparation → measurement and layout → installation of formwork → binding of steel bars → layered pouring of concrete


4、 Construction sequence of tie beams, columns, and cover beams


1. Construction sequence of tie beams (underwater)


Construction preparation → cofferdam pumping → installation of bottom and side formwork → reinforcement binding → pouring and curing of concrete


2. Construction sequence of columns


Construction preparation → Scaffolding support → Binding steel bars → Installing formwork → Pouring concrete for curing


3. Construction sequence of cover beam


Construction preparation → Support installation → Laying bottom plate → Binding steel bars → Installing side formwork → Pouring concrete for curing → Removing support


5、 Construction sequence of precast beams and slabs (prestressed beams and slabs)


Foundation treatment → Pouring pedestal → Installing slab beams and placing corrugated pipe samples → Binding steel bars and installing corrugated pipes → Pouring concrete bottom plate → Placing inner core formwork → Pouring concrete → Taking mold core → Cleaning holes and curing → threading prestressed tendon bundles (steel hinge lines) → Tensioning → Grouting and pouring head concrete


6、 Construction sequence of precast beams and slabs


Measurement and layout → guide frame assembly in place → prefabricated beams and slabs transported to the site → precise layout and installation of supports in place → installation of beams and slabs in place → acceptance inspection


7、 Construction sequence from simple support to continuous construction


Set up temporary supports and install beams and slabs → Install permanent supports and install bottom formwork → Bind steel bars according to the construction drawing of the cast-in-place section, and design continuous longitudinal steel bars → Install prestressed corrugated pipes → Erect side formwork → Pour the cast-in-place section (concrete needs to be reinforced with high-efficiency water reducing agent, using micro expansion cement, and compacted by vibration) → Timely curing → After the strength of the cast-in-place concrete reaches 100% of the design strength, tension the prestressed continuous bundle → Grouting → Remove temporary supports → Connect the beams and slabs horizontally → Lay the bridge deck steel mesh (the longitudinal steel bars of the steel mesh continuously pass through the cast-in-place section) → Pour the bridge deck concrete


8、 Construction sequence of bridge deck engineering


Install drain pipe → pour guardrail concrete → bind bridge deck steel bars → mix and pour concrete → install guardrail → set expansion joints


9、 Construction sequence of bridge channel


Measurement and layout → cofferdam pumping → manual excavation of foundation pit with excavator → foundation pit shaping → pouring of rubble concrete foundation → pouring of rubble concrete abutment → pouring of abutment cap → hoisting of beams and slabs → construction of bridge deck system → maintenance


10、 Construction sequence of box culvert


Measurement and layout → manual excavation of foundation pit with excavator → foundation pit shaping → laying of bottom slab concrete → formwork erection → first concrete pouring of culvert body 30cm above the bottom slab → formwork erection → second concrete pouring of remaining parts → curing → backfilling